Release time:2020-06-16 14:31Number of visits:405times
Recently, the consortium of CSCEC and China Construction Third Engineering Bureau Group Co., Ltd. won the bid for Chengdu rail transit line 27 phase I project, with a bid amount of 9.358 billion yuan.
The first phase of Chengdu rail transit line 27 starts from Xiangcheng Avenue station and ends at heyuanmen station. The total length of the line is 24.86 km, of which the elevated line is about 7.51 km, with 6 stations; the underground line is 17.35 km, with 17 stations, 1 vehicle base, 2 main substations, and the control center shares the new network control center. After the completion of the project, it will strengthen the traffic links between the northern area of Chengdu and the central urban area, promote the "northern transformation" of the city, expand the service level of rapid rail transit, and improve the public transport travel conditions of residents along the line.
Telephone: 0371-55153886/0394-8682999
E-mail: hnhddlkj@163.com
Address:Xihua economic Development Zone, Henan